11 Dec 2022

181

How to Calculate Earned Value Management (EVM)

Format: APA

Academic level: College

Paper type: Math Problem

Words: 388

Pages: 1

Downloads: 0

With reference to the diagram below, it can be inferred that the project is currently: 

Ahead of schedule and under budget, 

Ahead of schedule and over budget, 

Behind schedule and under budget, 

Behind schedule and over budget 

From the graph;

Also,

Thus, the project is behind schedule and over budget. Therefore the correct answer is D. 

With reference to the diagram below, it can be inferred that the project is currently: 

ahead of schedule and under budget, 

ahead of schedule and over budget, 

behind schedule and under budget, 

behind schedule and over budget 

From the graph;

Also,

Therefore the project is behind schedule and under budget. Thus, the correct answer is C. 

With reference to the diagram below, it can be inferred that the project is currently: 

ahead of schedule and under budget, 

ahead of schedule and over budget, 

behind schedule and under budget, 

behind schedule and over budget 

From the graph;

Also,

Therefore, the project is ahead of schedule and over budget. Thus, the correct answer is B. 

If a project has a Schedule Performance Index (SPI) of 0.90, this means that: 

a) 90% of the work planned to date has been completed. 

b) 90% of the work of the whole project has been completed. 

c) 90% of the budget planned to date has been spent. 

d) 90% of the project budget has been spent. 

The SPI represents the performance of a project represents how close the project or work is being completed compared to the schedule. It is the ration of the earned value to the planned value, i.e., . If the value of SPI is 1, it means the project is 100% of the scheduled work tofate is complete. Thus, if the SPI is 0.90, 90% of the scheduled work has been completed to date. Thus, the correct answer is A. 

A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of .80. The project is currently 

It’s time to jumpstart your paper!

Delegate your assignment to our experts and they will do the rest.

Get custom essay

Therefore the project is “behind schedule and over budget.” 

A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)? 

Therefore,

A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Cost Variance (CV)? 

Therefore,  

A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Schedule Performance Index (SPI)? 

A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Cost Performance Index (CPI)? 

You are the project manager of a housing project in which a total of 10 houses are to be built over 10 months (1 house per month). The total budget for the housing project is $1,000,000. The project is now at the end of the sixth month with five houses built and $500,000 spent. The project is behind schedule owing to a work strike for a month. The Cost Performance Index (CPI) for the project is 

From the question; 

Therefore,

Illustration
Cite this page

Select style:

Reference

StudyBounty. (2023, September 14). How to Calculate Earned Value Management (EVM).
https://studybounty.com/how-to-calculate-earned-value-management-evm-math-problem

illustration

Related essays

We post free essay examples for college on a regular basis. Stay in the know!

17 Sep 2023
Maths

Bernhard Riemann's Life and Contribution to Mathematics

Introduction Riemann Bernhard was an extraordinary mathematics professor at Göttingen, where he did most of his work in geometry, number theory, real as well as complex analysis. Having a strict Christian...

Words: 2630

Pages: 12

Views: 43

17 Sep 2023
Maths

How to Solve Problems: The 4-Step Problem Solving Process

Lesson Topic: Addition and Subtraction Grade: K-2nd Subject: Math Time: 40 minutes Introduction Problem solving provides a framework for developing higher-order thinking skills. However, many students...

Words: 598

Pages: 2

Views: 446

17 Sep 2023
Maths

What is the Goodness of Fit Test?

Null hypothesis, H0: The candies are uniformly distributed Alternative hypothesis, H1: The candies are not uniformly distributed. Chi-square = } Degrees of freedom = No. of groups-1= 6-1 =5 =0.0

Words: 79

Pages: 3

Views: 81

17 Sep 2023
Maths

Managerial Ethics in Financial Analysis and Accounting

Companies try to increase their value by using effectively all the resources provided to them by regulators, debtors, and shareholders. Mangers have fiduciary responsibilities and duties, which affects how they...

Words: 276

Pages: 1

Views: 56

17 Sep 2023
Maths

Using and Understanding Mathematics: Prologue Order of Operation

Order of operations involves addition, subtraction, multiplication, division, squaring, and more. The importance of the concept is understanding the order in which to solve a problem. If you calculate in the wrong...

Words: 143

Pages: 1

Views: 414

17 Sep 2023
Maths

Workplace Diversification at Coca Cola

The idea of incorporating both domestic and international clients has created a need for businesses to diversify their workforce. In the past decades, the nature of various workplaces featured members of a similar...

Words: 926

Pages: 3

Views: 90

illustration

Running out of time?

Entrust your assignment to proficient writers and receive TOP-quality paper before the deadline is over.

Illustration