With reference to the diagram below, it can be inferred that the project is currently:
Ahead of schedule and under budget,
Ahead of schedule and over budget,
Behind schedule and under budget,
Behind schedule and over budget
From the graph;
Also,
Thus, the project is behind schedule and over budget. Therefore the correct answer is D.
With reference to the diagram below, it can be inferred that the project is currently:
ahead of schedule and under budget,
ahead of schedule and over budget,
behind schedule and under budget,
behind schedule and over budget
From the graph;
Also,
Therefore the project is behind schedule and under budget. Thus, the correct answer is C.
With reference to the diagram below, it can be inferred that the project is currently:
ahead of schedule and under budget,
ahead of schedule and over budget,
behind schedule and under budget,
behind schedule and over budget
From the graph;
Also,
Therefore, the project is ahead of schedule and over budget. Thus, the correct answer is B.
If a project has a Schedule Performance Index (SPI) of 0.90, this means that:
a) 90% of the work planned to date has been completed.
b) 90% of the work of the whole project has been completed.
c) 90% of the budget planned to date has been spent.
d) 90% of the project budget has been spent.
The SPI represents the performance of a project represents how close the project or work is being completed compared to the schedule. It is the ration of the earned value to the planned value, i.e., . If the value of SPI is 1, it means the project is 100% of the scheduled work tofate is complete. Thus, if the SPI is 0.90, 90% of the scheduled work has been completed to date. Thus, the correct answer is A.
A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of .80. The project is currently
Delegate your assignment to our experts and they will do the rest.
Therefore the project is “behind schedule and over budget.”
A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)?
Therefore,
A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Cost Variance (CV)?
Therefore,
A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Schedule Performance Index (SPI)?
A project with Earned Value (EV) = $250, Actual Cost (AC) = $200 and Planned Value (PV) = $350. What is the Cost Performance Index (CPI)?
You are the project manager of a housing project in which a total of 10 houses are to be built over 10 months (1 house per month). The total budget for the housing project is $1,000,000. The project is now at the end of the sixth month with five houses built and $500,000 spent. The project is behind schedule owing to a work strike for a month. The Cost Performance Index (CPI) for the project is
From the question;
Therefore,