The hookah lounge project is set to be complete by 9/12/2018, and this will add on to the number of similar establishments in the United States of America. The main objective of coming up with this project was derived from the inspiration whereby a majority of people are into the entertainment industry. In addition to this, it is apparent that most individuals would not mind to spend extra income in order to have a fun experience. A variety of exotic varieties of entertainment will be made available for customers. 

Critical Path 

The critical path for the development will involve a series of steps, ranging from the initial site location through to the construction process. The initial process will involve setting up all the necessary building tools as a team of other people seek to find out what people are really interested in in the industry. This will ensure that all the necessary luxuries are set up in order to accommodate clients` needs. Also, an ideal location for the project has to be established to avoid conflicting with other similar entertainment hotspots. Besides, nowadays most of the people are eager to move out of the bustling city and into the suburbs to enjoy spending quality times with those close to them. 

It’s time to jumpstart your paper!

Delegate your assignment to our experts and they will do the rest.

Get custom essay

Staffing and Non-Staffing 

For the hookah lounge, the staffing segment of the firm requires to hire various specialist for the outbound segment. Some of the people required are: Sales agent, a Customer Care representative and also a manager. In addition, an outbound trainer and supervisor will hired for the inbound sector. Further still, in order to ensure that the staffing will function appropriately, effective resources such as some infrastructure will be put in place. This might involve resources such as computers and other accessories. 

Slack for the Project 

Besides, the slack for this project is 2 days on average. This is due to the fact that every activity is linked to the next and, therefore, there should be no room left for activities unattended. It is also imperative that the project is completed in time in order for the business to begin. Since all the relevant materials will be made available, skilled and consistent planning will ascertain that the development is done within the required duration of time. In case, a particular activity takes longer than expected, other subsequent tasks will be done in a faster means. 

In relation to the above, one of the activities that is likely to have the greatest slack is the constructions of the concrete slabs, walls, and columns. This is due to the fact that ample amount of time will be required in order to ensure that there is a lot of dexterity on the structures which need to be formidable in order for other works to fit in exclusively. 

Activities likely to Impact on the Completion 

Additionally, market research is bound to be undertaken throughout the entire duration and also after the project. Further still, designing will also need a lot of efficacy. The idea of having to obtain all the desirable artifacts that will make the building stand out from the rest. Besides, there is also a lot of uncertainty regarding the required duration of time that it will take the authorities to approve the project in order for it to begin. In order for everything to proceed on successfully, it would be advisable to have ample time to plan in advance so that every activity will be undertaken smoothly and with little or no interference. 

Finally, in order for the project to be more complete, it would be resourceful to seek guidance from qualified professionals. One should also make necessary assessment on the best places to acquire quality equipment at the most cost-friendly prices. Some natural accessories would also make the development have some authentic taste thus making it more desirable. Once this has been done, the project will end up being prosperous. 

Activities 

ID 

Activity 

Predecessor 

Time Period 

 

Architectural design 

Andrew 

7 days 

Creation of the draft for the design 

Andrew 

2 days 

Preparing the documents to be used in the construction 

Andrew 

3 days 

Agreeing on the architectural plan 

Andrew 

3 days 

Signing the agreement 

Andrew 

1 day 

Site Utility location 

Andrew 

1 day 

Get a Notice to Proceed 

Andrew 

1 day 

 

The Construction phase 

   

Clearing site for Construction 

John 

4 days 

Construct Temporary Structure next to proposed site for Storage of materials 

John 

3 days 

Procurement of Building materials 

John 

1 day 

10 

Excavation 

John 

2 days 

11 

Creating the Foundation 

John 

3 days 

12 

Pouring Concrete 

John 

1 day 

13 

Level the Concrete 

John 

1 day 

14 

Creating the Ground Floor 

John 

2 days 

15 

Coming up with the walls for the first floor 

John 

3 days 

16 

Establishing roofing structure 

John 

2 days 

17 

1 st Floor 

John 

2 days 

18 

Creating walls to the terrace 

John 

1 day 

19 

Coming up with the Roof 

Landry 

2 days 

20 

Mounting Doors 

Landry 

1 day 

21 

Mechanical Light Installation 

Piper 

1 day 

 

Finishing Phase 

   

22 

Decorations 

Cole 

3 days 

23 

Decorating the wall 

Cole 

2 days 

24 

Furniture installation and decoration 

Cole 

3 days 

25 

Installation of Tiles 

Cole 

2 days 

26 

Installation of Granite Cladding 

Cole 

1 day 

27 

Exterior Finishes 

Cole 

1 day 

28 

Installing Entertainment Equipment 

Cole 

1 day 

29 

Interior Design 

Cole 

8 days 

30 

Fitting artifacts and other Memorabilia 

Cole 

1 day 

31 

Construction of perimeter Wall 

Cole 

2 days 

32 

Cabro installation around the premises 

Cole 

2 days 

33 

Inspection 

Cole 

1 day 

Illustration
Cite this page

Select style:

Reference

StudyBounty. (2023, September 14). How to Create a Project Schedule for a Hookah Lounge Bar .
https://studybounty.com/how-to-create-a-project-schedule-for-the-hookah-lounge-bar-assignment

illustration

Related essays

We post free essay examples for college on a regular basis. Stay in the know!

How AI Can Help Retailers Solve Business Problems

The global marketplace is currently more integrated than ever before. This situation presents a never-before experienced opportunity for retailers. Multinational organizations whose sole basis is the internet have...

Words: 2700

Pages: 5

Views: 138

The Natural Organizational Model and the Informal Groups

The nature of an organization is based on different factors such as the environment it is set up in. also, the type of activity it undertakes. This paper will examine the natural organizational model, the informal...

Words: 3009

Pages: 10

Views: 240

Why Pinkberry should focus on making orange and yellow the two prevailing colours

The fact that Pinkberry has evolved from a storefront to a nationally recognized brand makes this franchise of frozen dessert yogurt shops an example to be followed. Yes, the personality of a brand created a platform...

Words: 582

Pages: 2

Views: 94

Ford Motors: Board Presentation For Electric and Hybrid cars Production

Executive Summary The motor vehicle industry in America and worldwide is highly competitive with major players no longer enjoying the dominance that they had had before. Innovation and identification of trends...

Words: 1088

Pages: 4

Views: 130

Home Remodel Project Plan

Project Overview Home remodeling is one of the notable key projects undertake through project management, as a project manager is expected to come up with a clear plan that would help in meeting the expected...

Words: 2152

Pages: 8

Views: 69

How Airbnb Achieved Success

Hospitality industry includes firms that provide lodging and dining services for customers. Many of the businesses in the travel and hospitality industry offer customers with prepared meals, accommodation, snacks,...

Words: 906

Pages: 3

Views: 63

illustration

Running out of time?

Entrust your assignment to proficient writers and receive TOP-quality paper before the deadline is over.

Illustration